Timeline

Construction Header


This page provides a timeline for the Elementary Campus building and renovation projects. These dates are subject to change and may be adjusted as the projects progress.



Estimated Timeline


June 2017 -
Elementary Campus Project authorization

June 2017 - May 2018 Design Development Phase
  • Sloan Renovations (Primary grades K-2)
  • New Intermediate School (grades 3-5)

April 2018 - 
Approval to bid project

May 2018 -
Bid Openings

August 2018 -
Bid Award/Ground Breaking

June 2018 -
Bids Awarded

October 18 -
Bid New Construction 3-5 Intermediate Building 

August 2018 - August 2020 -
Sloan Renovation Construction Phase

August 2020 -
Grand Opening (tentative)




Future Projects:



High School Renovations & Additions - TBD         
  • Stadium Upgrades
  • Potential Community Health & Wellness Center
  • Athletic Fields
  • Campus Reorganization

 

Middle School Renovations - TBD